DoD services submit Program Objectives Memoranda (POM) to OSD during which PPBE phase?

Prepare for the Program Management Practitioner Certification (PMT 4800V) Exam with flashcards and multiple choice questions, complete with hints and explanations. Ace your certification exam!

Multiple Choice

DoD services submit Program Objectives Memoranda (POM) to OSD during which PPBE phase?

Explanation:
In the DoD PPBE process, program plans and resource requests move through distinct phases. Program Objective Memoranda are produced during the Programming phase. This is the phase where the services translate strategic guidance into concrete programs and resource needs, outlining the manpower, procurement, research, and other resources required across the future years of the FYDP. These POMs are submitted to OSD to shape and align the Department’s proposed programs before the Budgeting phase, where the budget is built, and before Execution, where funds are actually spent.

In the DoD PPBE process, program plans and resource requests move through distinct phases. Program Objective Memoranda are produced during the Programming phase. This is the phase where the services translate strategic guidance into concrete programs and resource needs, outlining the manpower, procurement, research, and other resources required across the future years of the FYDP. These POMs are submitted to OSD to shape and align the Department’s proposed programs before the Budgeting phase, where the budget is built, and before Execution, where funds are actually spent.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy