During the Developmental Test (DT) effort, the purpose of verification is to determine ____________.

Prepare for the Program Management Practitioner Certification (PMT 4800V) Exam with flashcards and multiple choice questions, complete with hints and explanations. Ace your certification exam!

Multiple Choice

During the Developmental Test (DT) effort, the purpose of verification is to determine ____________.

Explanation:
Verification during Developmental Test confirms that the system is built to its defined specifications, meaning the design requirements are met and the product aligns with the build-to criteria. This is about building the product right. It’s not about whether the system will solve the user’s problem (that’s validation or user acceptance), nor about overall lifecycle cost, or performance in field conditions, which are addressed in other activities.

Verification during Developmental Test confirms that the system is built to its defined specifications, meaning the design requirements are met and the product aligns with the build-to criteria. This is about building the product right. It’s not about whether the system will solve the user’s problem (that’s validation or user acceptance), nor about overall lifecycle cost, or performance in field conditions, which are addressed in other activities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy