When Congress does not appropriate sufficient funds to cover the cost of work to be performed under a contract, the Government may:

Prepare for the Program Management Practitioner Certification (PMT 4800V) Exam with flashcards and multiple choice questions, complete with hints and explanations. Ace your certification exam!

Multiple Choice

When Congress does not appropriate sufficient funds to cover the cost of work to be performed under a contract, the Government may:

Explanation:
When funds are not appropriated to cover the work, the government can end the contract for convenience. This option lets the government pause or stop the work without accusing the contractor of fault, simply because there isn’t enough funding to continue. It’s different from termination for default, which happens when the contractor fails to perform as required; suspension is only a temporary pause that assumes funding will resume later; renegotiation isn’t a remedy used to address funding shortfalls. In a termination for convenience, the government typically outlines what costs are allowable for the contractor to recover and stops further work, avoiding an obligation to fund the unperformed portion.

When funds are not appropriated to cover the work, the government can end the contract for convenience. This option lets the government pause or stop the work without accusing the contractor of fault, simply because there isn’t enough funding to continue. It’s different from termination for default, which happens when the contractor fails to perform as required; suspension is only a temporary pause that assumes funding will resume later; renegotiation isn’t a remedy used to address funding shortfalls. In a termination for convenience, the government typically outlines what costs are allowable for the contractor to recover and stops further work, avoiding an obligation to fund the unperformed portion.